Christopher Burke
USA Guide 2024
Band 2 : Construction
Email address
[email protected]Contact number
+17034540178Share profile
Band 2
About
Provided by Christopher Burke
Practice Areas
Chris Burke has over 20 years of experience litigating construction disputes both domestically and internationally. Chris has tried multiple disputes through final award, with amounts in dispute of over US$1 billion.
Chris represents clients in state and federal courts and in arbitration proceedings, and has considerable experience with international dispute resolution. Chris represents owners, general contractors, construction managers, and subcontractors through the various stages of dispute resolution, from claim preservation through trial.
Before maturation of the litigation process, Chris works with his clients to avoid costly disputes by resolving issues at the project level. Once litigation is inevitable, however, Chris handles all aspects of the dispute process. He is a seasoned litigator who protects his clients' economic interests while preparing for the best presentation at trial should a matter "go the distance." He also advises clients on non-contentious matters, including contract drafting.
Chris is a frequent author and speaker in the construction law space and is active in both the American Bar Association and International Bar Association.
Chris graduated cum laude from Yale University and later from the University of Virginia School of Law, where he served as a Dillard Fellow Legal Research and Writing Instructor.
Professional Memberships
American Bar Association
• Forum on Construction Law
o Co-Chair, 2020 and 2023 Trial Academy Programs
o Associate Editor, The Construction Lawyer
• Litigation Section
• Public Contract Law Section
International Bar Association
• International Construction Projects Committee
Virginia State Bar
• Construction and Public Contracts Law Section
Publications
Co-Author: Chapter 9, Design-Build Contracting with the Federal Government, in Design Build, Public-Private Partnerships, and Collaboration Handbook (Wolters Kluwer) (3d ed. 2022).
Co-Author: Chapter 10, Design-Build Contracting with the Federal Government, in 2019 Construction Law Update (Wolters Kluwer) (2019).
Co-Editor: American Bar Association Forum on Construction Law Division 13 (Government Construction) newsletter (June 2016 – June 2018).
Co-Author: Chapter 25, Federal Government Construction Contracts Outside the United States, in Forum on Construction Law, American Bar Association, Federal Government Construction Contracts (3d ed. 2017).
Co-Author: “Time Is on (Their) Side: The United Kingdom’s Society of Construction Law’s Delay and Disruption Protocol 2.0,” The Construction Lawyer, Volume 37, Number 4 (Fall 2017).
Experience
Representing an ENR U.S. Top 20 general contractor in a dispute with a museum owner. The case is pending before the United States District Court for the District of Maryland.
Represented a contractor in a AAA / ICDR dispute with an EPC contractor on a 674MW natural gas-fired combined-cycle plant in Massachusetts. Chris served as co-lead trial counsel and following a multi-week evidentiary hearing, Chris’s client received a Final Award of over US$25 million on its claims of, among other things, lost productivity and change order work. Chris’s client was also awarded its attorneys’ fees and costs.
Represented an EPC Contractor in an ICC Arbitration dispute with a subcontractor on a 600MW coal-fired plant in South America. Chris served as lead trial counsel and following a multi-week evidentiary hearing, Chris’s client received a Final Award upholding his client’s default termination, awarding completion costs and liquidated damages in excess of US$11 million, and denying nearly all of the subcontractor’s US$30 million delay and disruption claims. Chris’s client was also awarded its attorneys’ fees and costs.
Represented a general contractor joint venture (comprised of two ENR U.S. Top 20 contractors and an ENR Top 100 contractor) in an arbitration concerning the design and construction of a US$1.5 billion data center in Utah. The eight-party case proceeded through one week of an American Arbitration Association evidentiary hearing before reaching settlement after Chris’s joint venture client put on its affirmative case.
Represented a general contractor concerning the construction of a new 18-story courthouse in Las Vegas, NV. Following a 10-week arbitration hearing wherein Chris served as trial counsel, Chris’s client obtained a Final Award of $52.7 million on its affirmative claims and defeated nearly all of Owner Clark County's $60 million counterclaim.
Represented ENR U.S. Top 50 contractor engaged in an ICC Arbitration dispute with its subcontractor over the construction of a 100MW power plant in Afghanistan. Chris served as trial counsel.
Represented an ENR U.S. Top 10 contractor engaged in a dispute with its subcontractor over the engineering and construction of a 600MW petroleum coal-fired CFB power plant. Following the first five-week phase of a scheduled eight-week arbitration hearing, during which Chris served as trial counsel, Chris's client and the opposing party were able to achieve a confidential settlement of their disputes.
Represented an EPC contractor in an ICC Arbitration dispute with its subcontractor over performance on a 300MW solar power plant in Arizona. The parties reached a confidential settlement prior to the evidentiary hearing of the matter.
Represented an at-risk construction manager concerning the construction of a luxury condominium project in New York City. As co-lead trial counsel through a nearly three-week arbitration hearing, Chris helped the construction manager obtain a Final Award of over $10 million on its affirmative claims. The Final Award overturned the Owner's improper default termination claim, and dismissed the Owner's $120 million counterclaim in its entirety.
Represented a general contractor in Utah Federal Court against an Owner concerning the construction of a wastewater treatment facility. Serving as lead counsel, Chris negotiated a favorable settlement for his client prior to trial.
Represented a general contractor concerning the construction of tunnels and shafts on the McCook Reservoir Project (Chicago, IL). A settlement was achieved prior to a hearing scheduled before the Armed Services Board of Contract Appeals.
Education
Yale University
B.A., cum laude
1999
University of Virginia
J.D.
2002